The project consisted of a steel structure construction (on existing two storey reinforced car park), electrical and mechanical works of a shopping mall which is located in Baku.
The building consists of 4 storey and total covered area is 8.000 sqm. The work covered steel construction, common areas (excluding shops) and facade architectural finishing works, mechanical, electrical and landscaping works.
Scope of Work
Construction of steel structure system,
Execution of roof finishing works;
- Thermal insulation,
- Water insulation,
- Roof cladding works.
Installation of all electrical systems;
- Transformer substations and MV switchgear,
- Diesel generators,
- Main distribution / MCC / Sub distribution boards,
- Lighting (Internal and External), Power distribution,
- Telecommunications,
- Fire Alarm and protection,
- Earthing and lightning protection,
- Low voltage systems (telephone, security/intruder alarm, CCTV).
Installation of all mechanical systems (HVAC, plumbing, sanitation and sewage systems);
- HVAC systems (heating/air conditioning/ventilation),
- Cold / Hot water supply, storage, piping,
- Sewage system collection pipes and pumps,
- HVAC ducting, insulation, piping works,
- Boiler / Chiller systems related works,
- Fire fighting system pumps and piping,
- Sprinkler system,
- Rainwater drainage,
- Elevators (Panoramic).
Execution of all exterior finishing works;
- Curtain wall glazing facade,
- GRC facade elements.
Execution of common areas interior finishing works;
- Natural stone floor covering works,
- Wooden wall covering works,
- Gypsumboard suspended ceiling,
- Mineral wool suspended ceiling,
- 3 dimensional pre-formed lexan suspended ceiling,
- Floor and wall ceramic tiles,
- Decorative painting,
- Epoxy floor covering.