Project Description
Project included the execution of maintenance of break water crown walls and belt conveyor column pedestals of Lisco Harbour.
Scope of Work
Excavation around the conveyor belt column pedestal up to the required depth necessary for maintenance
Backfilling, levelling and compacting of the area surrounding each column pedestal
Hauling and disposal of damaged concrete and steel reinforcement to the assigned area determined by LISCO
Electro-mechanical and hand demolition of reinforced concrete for the damaged breakwater walls, bearing in mind the concrete cover shall be at least 4 cm for the steel reinforcement
Electro-mechanical and hand demolition of reinforced concrete for the conveyor belt columns pedestals
Prepare and fixing of steel reinforcement to replace the damaged steel bars in addition to the sand blasting or wire brush cleaning for the remaining steel bars as per BS standards.
Client
LISCO
Date of Completion
January, 2004