Project Description
The project included the construction of a 490 m long and 42 m wide 2x3 vehicular lanes and 2x1 walkways bridge supported by 114 tubular steel piles 2 m in diameter, with lengths extending down to 80 m below water level, which was on of the largest foundation system of the World.
The deck consisted of two 193 m parts prestressed reinforced concrete double deckers supported by tubular steel piles and a 2 x 40.5 m span bascule supported by two reinforced concrete caissons of 5,500 tonnes built underwater on tubular steel piles.
Date of Completion
December, 1994
Management Role of TML Principals
Eser TÜMEN President of the Contracting Company
H. Ersin TAKLA Sr. Vice Pres. of the Contracting Company, Operations
R.Oguz BOZKURT Sr. Vice Pres. of the Contracting Company, Planning
Yüksel TIRYAKIOGLU Project Group Manager