In this episode, Mr. Takla takes us through his journey in Libya, which began in 1973 — following years from TML's first project, the renovation of Garyan Hospital in 1992, to milestone works like the Misurata Piled Discharge Berths. He shares his experience in Libya, the country that opened the door for Turkish contracting abroad, along with his perspective on today's landscape and what lies ahead.

He also reflects on his role at the Libya-Turkey Business Council, founded in 2004, and on how economic relations between the two countries have evolved over the years.

"Business and strong relationships don't grow in the office, at the table. To bring business to the table, you need to step outside those four walls and get into the field."

A story of 52 years of legacy, a journey, and values passed down from one generation to the next.

Stay tuned for the next episodes in the series.

September, 2026
TML's Story: From Generation to Generation with 3 Perspectives – First Episode
May, 2026
Tetrapod Works from Aerial
April, 2026
More and More Tetrapods Everyday
March, 2026
Tetrapod Works in Progress
March, 2026
Works Nearing Completion at Omar Mouhtar University
November, 2025
Final Acceptance Certificate Received
October, 2025
TUV ISO Audits Have Been Successfully Completed
August, 2025
New Contract Signed in Libya
July, 2025
Provisional Acceptance Certificate received
June, 2025
Back to Business at Omar Mouhtar University.
March, 2025
TML Signed a Contract for the Works at Omar Mouhtar University in Al-Baida, Libya.
January, 2025
Phase 4 Works in Progress
October, 2024
Provisional Acceptance Certificate received
October, 2023
New Contract Signed in Libya
August, 2023
Works Moving Forward in Misurata
January, 2023
Provisional Acceptance Certificate received
December, 2022
Works Moving Forward in Misurata (1)
December, 2022
Works Moving Forward in Misurata (2)
December, 2022
Works Moving Forward in Misurata (3)
October, 2022
Provisional Acceptance Certificate received
September, 2022
Back to Action for Misurata Container Storage Yard
June, 2022
New Contract signed in Libya
November, 2021
Provisional Acceptance Certificate received
October, 2021
Renewal of ISO Certificate
May, 2021
New project from LISCO
March, 2021
Works Moving Forward in Misurata
November, 2020
TML obtained ISO 45001:2018
July, 2020
Asphalt works in progress
February, 2020
Back to Action in Misurata
January, 2020
Subsea Installation Works Completed in Algeria
January, 2020
Provisional Acceptance Certificate received
September, 2019
Repair Works of LISCO Berth in progress
May, 2019
Substantial Completion achieved in Kuwait
March, 2019
New Contract Signed in Libya
February, 2019
Outstanding Performance Award received in Kuwait
December, 2018
State-of-the-art technique in HDPE pipe installing
December, 2018
Offshore Works of Doha Desalination Plant, Kuwait
November, 2018
Offshore Works of the Mostaganem CCPP, Algeria
November, 2018
TML at LISCO’s New Bar Mill Opening Ceremony
September, 2018
Subsea HDPE Pipe installation works in progress
April, 2018
Final Acceptance Certificate obtained
March, 2018
Subsea GRP Pipe Installation works in progress
December, 2017
Final Acceptance Certificate obtained
April, 2017
First Project in Algeria
January, 2017
First Project in Kuwait
December, 2015
TML in the Sultanate of Oman
December, 2015
Baku Gateway Building Delivered
October, 2015
Renewal of ISO Certificate
August, 2014
TML on the ENR Top 250 List
July, 2014
Baku Gateway Building Project
June, 2014
Misurata Free Zone Container Storage Yard
March, 2014
The Ribbon-Cutting Ceremony at the New Dock
February, 2014
MFZA Infrastructure Asphalt Works Began
December, 2013
Baku Shipyard Project Delivered
November, 2013
Renewal of ISO Certificates
May, 2013
Misurata Free Zone Infrastructure Works Resuming
February, 2013
New Bar Rolling Mill Erection Works Project Signed
December, 2012
Completion of Misurata Police Station Project
January, 2012
Baku Gateway Building Project Signed
January, 2012
MFZA Container Terminal Works Resuming
February, 2011
Uprising in Libya... Successfull Evacuation