Container Storage Yard


Construction Of Container Storage Yard Phase-I Including Utility Services To Berths No:16-17-18-19-20 At Misurata Free Zone

Client : Misurata Free Zone Company

Main Contractor : TML

Key Designer : ECAP’s Tender Design

Start Date : July 2014

Finish Date : October 2015

Key features of Work Scope:
The scope of project is the execution of the earthing and construction works of the container Storage Yard including Utility Services to Berths No: 16,17,18,19 and 20.

The project is located in Misurata, Libya. The project is owned by Misurata Free Zone Cpmpany and the main contractor is TML.

The works that are going to be performed for the construction of the berths are as follows:

Earthing works consisting of
Excavation: 6,739.00 m³
Filling with imported material: 20,649.00 m³
Filling 300 mm sub-base material: 20,480.00 m³
Construction of 55,525.00 m² * 0.35 m Concrete Pavement,
Construction of 665.00 m length Electrical Culvert,
Construction of 36 no’s Fire Water Manholes, 4 no’s Potable Water Manholes, 46 no’s Electric Manholes, 32 no’s Storm Water Manholes and 99 no’s Road Gullies,
Supply and Install approx. 15000 m various types of Triplex, PE and U-Pvc Pipes,
Construction of Sea Water Pump House to be made of Steel Structure with cladding, including all pipes, fittings and fire pumps,
Construction of 10 no’s 43 m and 6 no’s 28 m length High Mast Pole Foundations.