ACG Tank Farm Construction-1
ACG FFD Project, Phase 1 Tank Farm Construction
Client : AIOC-BP
Key Designer : Kellog Brown & Root
Consultant : Kellog Brown & Root
Start Date : February 2004
Finish Date : December 2004
Key features of Work Scope:
The scope of work consisted of:
· Civil scope associated with construction of the Tank Farm and Processing Area,
· Civil scope associated with the refurbishment of the SPS Quayside Berths (5 to7),
· Civil scope associated with construction of the Water Tank Base & Plinth,
· Site engineering activities, necessary to complete the works (As-built drawings).